Site Search

Melrose Park Sports Pavilion

The construction of a new sports pavilion that meets the participation demands and sporting clubs needs.

About this project

The Melrose Park change rooms and amenities are at the end of their useful life. Designs have been developed in consultation with the Melrose Football Club. The new sports pavilion building will address the identified amenity deficiencies such as lack of female change facilities, additional accessible public toilets, storage and community space with canteen facilities.

The NSW Government is providing $350,000 through an election commitment towards female friendly facilities. Council has been successful in securing $257,000 through Stronger Country Communities program round 4 for the project while Melrose Football Club is also contributing to the project.

Due the damaged caused to the existing building from fire, it was demolished. Temporary facilities have been funded through collaboration between the Melrose Football Club, Albury Wodonga Football Association and AlburyCity.

5 July 2024

Soffit linings, suspended ceilings and tiling are completed. Joinery, toilet fit out and internal painting has commenced.

MelroseSP-05-07

MelroseSP-05-07a

MelroseSP-24-05b

7 June 2024

MelroseSP-08-06-24

MelroseSP-08-06-24b

MelroseSP-08-06-24a

24 May 2024

Blockwork and roofing are nearing completion. Guttering is attached and work has commenced on the underside of the roof. Internal works continue.

MelroseSP-24-05

MelroseSP-24-05a

MelroseSP-24-05b

10 May 2024

Blockwork and service installation continues.  Roof work commenced this week.

MelroseSP-10-05

MelroseSP-10-05a

MelroseSP-10-05b

03 May 2024

MelroseSP-03-05

MelroseSP-03-05a

19 April 2024

Internal blockwork continues.

MelroseSP-19-04a

MelroseSP-19-04

5 April 2024

Framework construction is complete with internal blockwork underway.

MelroseSP-05-04

MelroseSP-05-04a

MelroseSP-05-04

29 March 2024

The steel framework has arrived on site. Installation has commenced.

MelrosePhSP29-03

MelrosePhSP29-03a

MelrosePhSP29-03b

1 March 2024

Melrose03-03

Melrose03-03a

16 February 2024

Excavation and formwork underway for the raft slab

Melrose16-2

Melrose16-2a

9 February 2024

Underground servicing is underway prior to preparing formwork for the raft slab.

Melrose9-2

Melrose9-2a

26 January 2024

On-ground works have commenced on the new sport pavilion.

Melrose26-1

Melrose26-1a

1 December 2023

At the Council meeting held on 27 November 2023, Council accepted the tender from Premier Building Construction Pty Ltd (PBC) for the construction of the Melrose Park Sports Pavilion.  Construction is scheduled to commence in early 2024.

18 August 2023

After a lengthy detailed design process, the construction tender was uploaded to Tenderlink today. Tenders close 12 September 2023. Following assessment, a report will be presented to Council recommending a preferred contractor.

1 April 2022

There has been delays in progressing the detailed design of the building however procurement processes are well underway now and scheduled to close on 22 April 2022. Following the engagement of the design consultant, a review of timelines for detailed design completion, construction Tender awarded, construction commencement and project completion will be undertaken.

18 February 2022

Detailed design process is underway with construction ender due to be advertised in coming months.

29 October 2021

The Review of  environmental factors has been determined. Work can now commence on detailed design

1 October 2021

The concept designs have been finalized with public exhibition process closed. The review of environmental factors is complete and awaiting determination.