Site Search

Building our City

Find out what current and planned works are happening in and around our city.

Updated: Thursday 29 September, 2022
  • Krautz Street – Maintenance grading/shoulder works are in progress.
  • Griffith Road – New kerb and gutter construction is complete.
  • Keating Court – Kerb and gutter works are continuing.
  • Mutsch Street – New kerb and gutter construction has commenced.
  • Albury Riverside Precinct – Progress on the remaining landscape works has slowed due to high Murray River levels.
  • Thurgoona Oval Sporting Pavilion – Installation of wall linings is ongoing, while waterproofing and tiling is scheduled to commence at the end of this week. Installation of roller doors is expected to begin next week.
  • Ernest Grant Park – Works in the play space area are ongoing, with the contractor commencing installation of play equipment.
  • Keene Street Reconstruction – Road base has been placed and kerb works are complete between Cadell Street and Borella Road, with landscaping and other concrete work underway. The final stage of the project is expected to commence next week between the Borella Service Road and Borella Road.
  • Sewer Rehabilitation Program – Sewer main cleaning and rehabilitation works are progressing.
  • Borella Road Retaining Wall – We’re waiting on the water level in the stormwater channel to subside before resuming works.
  • National Foresters Grove Amenities – Roof and wall frame installation is progressing well.
  • Union Road Pedestrian Refuges – Demolition of existing kerbing and pedestrian islands on the corner of Union Road and Bralgon Street are underway, with concreting works scheduled to begin next week.

You can find out more about our Major Projects here

Image of works

.