Wood Fired Oven Improvements

We'll use NSW Government funding to improve and expand this popular community facility at Hovell Tree Park.

About this project

The construction of the wood fired oven area project is now complete. The official opening of the project was held on Friday 13 November 2020.

Find out more about the community bake schedule.

The Wood Fired Oven at Hovell Tree Park holds a number of community bakes throughout the year.

To improve the experience for locals and visitors the following will be completed under the Regional Growth, Tourism and Environment Fund projects.

  • Extension of the Wood Fired Oven sheltered area and concrete under surfacing
  • Upgrade of water to the site
  • Provision of sewer at the shelter
  • Improved storm water drainage
  • Construction of storage for operations of the Wood Fired Oven
  • Upgrade of the electrical infrastructure for community events

Design development is complete with construction works commenced in October 2019.

13 November 2020

The opening of the Wood Fired Oven was held today. Thanks to students from St Patricks Public School who helped open the new area.

WFO Opening

WFO Openinga

WFO Openingb

2 October 2020

This week the finishing touches were completed on the wood fired oven shelters. The posts were clad with timber, seats and bins installed, barbecues connected, drinking fountain connected and small garden area planted. Th ovens are almost ready for the burning in process. Stay tuned for an opening date.

WFO 02-10a

WFO 02-10

WFO 02-10c

25 September 2020

Concrete works were completed this week. Drainage and irrigation works were also complete. Turf  has been laid around the site on the majority of the bare areas.

WFO 25-09

WFO 25-09a

18 September 2020

The majority of the concrete works is now complete. The plumbing and electrical fitt off works is scheduled to commence this week

WFO 18-09a

WFO 18-09a

4 September 2020

Concrete works continues under the new shelters

WFO 04-09

WFO 04-09a

28 August 2020

Concrete preparation continued under the new shelters. This first of the concreting works involved the construction of the seat adjacent to Noreuil Parade.

WFO 28-08

WFO 28-08a

14 August 2020

The brick work in the oven building is complete with the roof installed. The landscaping works has commenced with preparation work underway for the concreting while the servicing works continue.

WFO 14-08

WFO 14-08a

30 July 2020

Brickwork around the wood fired oven continued this week with the roof iron ready to be installed.

WFO 30-07

23 July 2020

The pizza ovens arrived today and were lifted into position. The brickwork can now be completed on this building.

WFO 23-07

17 July 2020

The electrical upgrade works has commenced with new mains power installed from Wodonga Place to the Wood Fired Oven. Works also continues on other servicing. Landscape works are due to commence soon.

WFO 17-07

3 July 2020

Roofing material installed on the new shelters. Pizza ovens have been ordered and are due to arrive this month.

WFO 03-07

26 June 2020

Scaffolding has been installed in readiness for installing the roofing material.The laying of pipes for servicing continues.

WFO 26-6

29 May 2020

The oven/storage area brickwork is almost complete. The  servicing of the site (water, sewer, electrical and stormwater) has commenced with the installation of underground conduits and pipes.

WFO 29-05

WFO 29-05b

1 May 2020

The steel structures have been erected while the brickwork continues on the oven/storage area.

WFO 01-05

WFO 01-05a

WFO 01-05b

20 March 2020

The site set out is complete with footings installed for the shelters and oven/storage area.

WFO 20-03

WFO 20-03a

6 March 2020

Demolition of the site continues with the removal of the old ovens and surrounding furniture. The existing shelters will be retained.

WFO 06-03

WFO 06-03a

31 January 2020

Demolition continued this week with the dismantling and removal of the redundant shelter. Steelwork for the new shelter is currently being manufactured off site.

WFO 31-01

24 January 2020

The wood fired oven upgrades have commenced. Temporary fencing has been erected with the pavers and picnic tables under the redundant shelter removed.

WFO 24-01

WFO 24-01a