Wagirra Trail Extension | AlburyCity
Site Search
Novel Coronavirus (COVID-19) Update

Read the latest update regarding our response to the novel coronavirus (COVID-19) situation.

Read more

Wagirra Trail Extension

Construction is underway on an additional 12kms of sealed pathway extending behind Wonga Wetlands.

About this project

The Wagirra Trail extension is one of the four major projects we're delivering in partnership with the NSW Government under the Regional Growth Environment and Tourism Fund.  All projects improve our connection with the Murray River and will be ready for us to enjoy by mid 2021.

The Wagirra Trail currently links the Union Bridge to Wonga Wetlands. Along the six kilometre trail you can view the 11 art pieces of the Yindyamarra Sculpture Walk,

We're now extending the trail to follow the banks of the Murray River around the perimeter of Wonga Wetlands.

The project will involve:

  • Construction of 12 KM of a 2.5 metre wide sealed trail
  • Installation of seating every kilometre
  • Bike racks
  • Directional signs
  • Picnic tables
  • Expansion of the Yindyamarra Sculpture Walk with five additional art pieces

Stage 1 - 4.3 Kilometres

Stage 2 - 8 Kilometres

The draft 2020-21 budget includes the final allocation of funding ($500,000) towards the construction of the Trail at Wonga Wetlands.

New canoe ramp

As part of the trail extension, we're building a canoe ramp for paddlers to access the Murray River.

Just off Waterview Road, the ramp extends into an anabranch that will give easy paddling access to the river in the warmer months when river levels are high.

The disability access-compliant facility will also include a small car park and turnaround point.

Open only to non-powered craft, the ramp will have bollards to prevent use by larger, powered boats.

It's been developed through Roads and Maritime Services Better Boating grant funding.

Updates

Trail Progress 30 March 2020

Construction phase - Stage 1Distance
Under construction 0 Metres
Base complete 800 Metre
Hot mix complete 3.5 Kilometres
Construction phase - Stage 2Distance
Under construction                                                                                               740 Metres
Base complete 2.1 Kilometres
Hot mix complete 4.2 Kilometres

Map 17-04-2020

17 April 2020

The streambank works in stage one is complete. Base construction of stage two continues with less than 500 metres to construct. Hot mix of  another section of stage two was completed this week. Tenders have closed for the bridges and are currently being assessed.

Section 1 - 17-04

Section 2 - 17-04

Section 2 - 17-04a

Section 2 - 17-04b

7 February 2020

The base of the final 550 metres of stage one has been constructed. Rocks are being transported in and will be placed along the streambank to assist in stabilising the bank. Stage 2 is progressing well over 2.5 kilometres of base completed. The Request for Quotation has been advertised for the bridges.

Section 1 - 07-02

Section 2 - 07-02

11 January 2020

The first two kilometres of stage two has had the hotmix laid.  Base preparation has moved north adjacent to where the bridges will be constructed.

Section 2 - 11-01

Section 2 - 11-01a

Section 2 - 11-01b

6 December 2019

Construction of stage 2 is well underway with 1.9 kilometres of the base constructed. The tender documents are being prepared for the bridges. The completion of the remaining 550 metres of stage 1 will commence when the streambank works in this area are complete.

Trail 6-12

Wagira River view 7-12

4 October 2019

700 metres of hotmix was laid this week. This completed 3.5 kilometres of trail. The base construction of 250 metres was also completed which leaves a further 550 metres to construct to finish stage 1.

13 September 2019

The base construction continues along the river while a further two more sections of hotmix has been completed. The canoe ramp is complete while the car park area is still under construction.

15 August 2019

Tree Planting along Waterview Road was undertaken as part of a Community tree planting day. The installation of hotmix was completed on a 600 metre section of trail along Waterview Road.

26 July 2019

Track construction has slowed due to the wet cooler weather. The concreting of the canoe ramp is complete and surrounding works underway. The adjacent hardstand will commence in August.

21 June 2019

Excavation works has continued on the trail along the woodlot area. Streambank works at points A and B are complete while construction has commenced on the canoe launching area near Waterview Road.

14 June 2019

Site preparation has commenced for tree planting along Waterview Road while streambank works has commenced at point A (refer map).

25 April 2019

Work continues on preparing the trail adjacent to the Murray River east of point B.

4 April 2019

A small section of trail base construction was completed at the junction of the lagoon and Murray River. Local Land Services will undertake some river revetment work (refer Map above A) prior to undertaking more trail construction work in this area. Works meets the Murray River. Trail construction has moved east (refer Map above B)

22 March 2019

A major portion of trail along Waterview Road base construction is now complete with link to Riverina Highway still to be done. Works will continue along the rive until the canoe launch facility is constructed .

15 March 2019

Works continues south along Waterview Road - excavation and preparation works

8 March 2019

Works continues on the Waterview Road section of the Trail. The base has been prepared for a short section from the bridge adjacent to the Riverina Highway..

16 February 2019

Base preparation has commenced along Waterview Road while it continues on the southern section of the Trail along the Murray River.

1 February 2019

The base of approximately 740 metres of trail has been constructed to date. Preparation of the next section is underway

Related Projects
Never miss an update
account_circle
mail_outline
* We'll never share your email with third parties