This project will involve the construction of new public toilet facilities and the first Changing Places Facility for the City.
The project involves the construction of a new toilet block with
The existing toilet block will be open during construction. It will be demolished after the completion of the project.
23 September 2022
The installation of the framework commenced this week
9 September 2022
Concrete slab is complete
22 August 2022
Service installation and concrete slab preparation well underway.
12 August 2022
On-ground works have commenced this week with the temporary fencing erected and foundation works underway.