JC King Park Sports Pavilion Project

The construction of the new sports pavilion is a partnership between AlburyCity and the Albury Netball Association. The project involves the demolition of the existing substandard buildings (clubroom and public toilets) and the construction of new multi purpose sports pavilion and associated public amenities.

Connelly Construction Services have been awarded the construction contract and works commenced in September 2018.

View the building designs

15 March 2019

Window installation is complete while the building service "rough-in" and internal cladding continues. The clean up and levelling around the front of the buildings has commenced

8 March 2019

The roof has been installed and the rough-in of building services has commenced. Windows have been installed while internal and external cladding has commenced.

22 February 2019

Structural steelwork and partition framing on the main sports pavilion are complete  The roof plumbers have performed their site measure to install the roof next week.

15 February 2019

Internal framework continues in the main sports pavilion while internal concrete walls are being installed in the amenities building.

.

8 February 2019

The majors work this week has occurred on the main sports pavilion. The roof steelwork continues to be erected. Internal wall framework is starting to set out the internal rooms while the footings have been installed for the verandah posts.

1 February 2019

The roof steelwork continued this week and the commencement of the internal wall framework. Earthworks have been undertaken around the main sports pavilion in readiness for the concreted viewing area

25 January 2019

The installation of steelwork on the main sports pavilion continued this week while the front concrete wall palls were also put into place.

18 January 2019

Works recommenced on the sports pavilion at JC King park. Steelworks starts on the main sports pavilion while minor works has occurred on the amenities area

21 December 2018

The concrete wall panels were erected this week on the main sports pavilion and the concrete floor poured. The contractor will now break for Christmas.

14 December 2018

The concrete slab in the changeroom section of the building has been poured while the concrete floor slab in the sports pavilion section is being prepared.

7 December 2018

The first of the concrete wall panels have been erected this week on the changeroom building. More to erected prior to Christmas

29 November 2018

Brickwork is complete around the main building while the concrete slab preparation works continues on the changeroom building

26 November 2018

Foundations are almost complete. Bricks are placed throughout the site and ready to be laid

11 November 2018

Works continues on the foundations and plumbing work of the new sports pavilion.

28 October 2018

Demolition is complete and pier foundation and plumbing works well underway.

6 October 2018

Demolition well underway with only the footings and existing power still to be demolished form the old clubroom. The old toilet block is partly demolished

22 September 2018

Site establishment is complete and demolition works commenced

.