JC King Park Sports Pavilion Project

The construction of the new sports pavilion is a partnership between AlburyCity and the Albury Netball Association. The project involves the demolition of the existing substandard buildings (clubroom and public toilets) and the construction of new multi purpose sports pavilion and associated public amenities.

Connelly Construction Services have been awarded the construction contract and works commenced in September 2018.

View the building designs

14 December 2018

The concrete slab in the changeroom section of the building has been poured while the concrete floor slab in the sports pavilion section is being prepared.

7 December 2018

The first of the concrete wall panels have been erected this week on the changeroom building. More to erected prior to Christmas

29 November 2018

Brickwork is complete around the main building while the concrete slab preparation works continues on the changeroom building

26 November 2018

Foundations are almost complete. Bricks are placed throughout the site and ready to be laid

11 November 2018

Works continues on the foundations and plumbing work of the new sports pavilion.

28 October 2018

Demolition is complete and pier foundation and plumbing works well underway.

6 October 2018

Demolition well underway with only the footings and existing power still to be demolished form the old clubroom. The old toilet block is partly demolished

22 September 2018

Site establishment is complete and demolition works commenced

.