Empowering Progress

We’re planning for the future, investing in a range of projects to strengthen Albury’s status as a national destination for life, work, culture, sport, entertainment and investment.
Image of road works sign
Holmwood Cross Drain Reconstruction

2021/2022 Budget: $300,000

Completion: December 2021

This project objective is to fully reconstruct the open concrete drain between Holmwood Cross and Albury TAFE.

Concept image
Albury Entertainment Centre Convention Wing Redevelopment

Completion: September 2021

We’re proposing a major redevelopment of the Albury Entertainment Centre (AEC) Convention Wing to create a leading regional events, conference and function venue.

Lauren Jackson Sports Centre Upgrade

Total budget: $11M

Completion: June 2023

Detailed investigations and planning for Stage 1 upgrades will be undertaken during 2019-2020 to ensure the facility is bought up to modern standards and accessible for all users.

Mate Street Beautification Project

Total budget: $900,000

Completion: May 2021

We’re planning important infrastructure and streetscape improvements on Mate Street between Urana Road and Tarakan Avenue.

Aerial view of the airport precinct
Airport Precinct Expansion

2021/2022 Budget: $700,000

Completion: June 2022

Works are underway on the expansion of the general aviation western precinct to meet future demand for airside lots.

NEXUS SIGN
NEXUS Industrial Precinct

2020/2021 Budget:

Total budget: $30M

Completion: December 2021

This exciting project will see the finalisation of infrastructure construction as part of the NEXUS Industrial Precinct, including the much anticipated Davey Road interchange.

Image of the Murray River
South Albury Levee (Australia Park)

2021/2022 Budget: $250,000

Completion: October 2021

This project is to construct/realign a portion of the South Albury Levee within Australia Park.

Image of the Albury Emergency Management Centre
Emergency Management Centre Stage 2

2021/2022 Budget: $400,000

Completion: June 2022

We are leading an innovative and ambitious approach to regional emergency services management with the establishment of a multi-purpose co-ordination, response and training facility at the Albury Airport.

Lavington Sports Ground Redevelopment

Total budget: $19.6M

Completion: 2021-2022

This major redevelopment will transform the Lavington Sports Ground into one of regional Australia's premier sporting facilities, capable of hosting local, regional, state and national carnivals, community sport and other events.

Road works image
Hawksview Road Construction

2021/2022 Budget: $500,000

Completion: March 2022

The project consists of a full reconstruction of Hawksview Road from Knoble Road to Annaconda Lane.

Image of the PumpHouse
PumpHouse Maker Space & Artist Workshop

2021/2022 Budget: $1.8M

Completion: June 2022

Albury’s historic pump house in Waterworks Road will be transformed into a mecca for artists and creators.

Image of water pipes
Water main to Wonga Wetlands

2021/2022 Budget: $820,000

Completion: June 2022

A 150mm water main will be constructed from Pemberton Street to Wonga Wetlands.

Image of a cat and dog
Animal Management Facility

2021/2022 Budget: $200,000

Completion: June 2022

Part two of this project will deliver the design for a modern regional animal management facility

Murray Park MP Final
Murray Park Play Space

2021/2022 Budget: $240,000

Total budget: $485,000

Completion: June 2022

This project will meet the request of Thurgoona residents for a new place for children to play at Murray Park Estate.

AWEC 21-11
Equestrian Centre Improvements

Total budget: $407,063

Completion: October 2020

This project involves the construction of covered stables, road works and camping area upgrades at the Albury Wodonga Equestrian Centre Thurgoona .

Image of new sewer pipes
Sewer Rehabilitation Program

2021/2022 Budget: $3.7M

Completion: June 2022

This year, the ongoing annual program will ensure the continued inspection of the network and rehabilitation works where necessary.

Image of erosion
Day Street Drain Reconstruction

Completion: April 2021

We’re reconstructing the Day Street storm water drain to improve the functionality, amenity and environmental impacts to the area.

Concept image of new car park at Australia Park
Australia Park Carparking

Total budget: $685,000

Completion: December 2021

This project will vastly improve car parking for visitors to our riverside parks.

Aerial image of the airport
Airport Taxiway Charlie - Stage 2

2021/2022 Budget: $3.05M

Completion: June 2022

Delays to landing and take-offs at the airport will be reduced and safety improved by the extension of Taxiway Charlie.

Existing building
Thurgoona Oval Change Room Upgrade

Total budget: $2.3M

Completion: November 2021

The project involves the construction of new change rooms for AFL and netball and associated public amenities

Image of Albury Swim Centre
Albury Swim Centre – Major Plant Replacement

Total budget: $400,000

Completion: August 2021

The consistent management of water quality at the Albury Swim Centre will be improved by the installation of six new filter units in the plant room.

EGP Exercise 21-1 zone 1
Thurgoona Outdoor Fitness Zone

Total budget: $228,840

Completion: December 2020

As part of the redevelopment of Ernest Grant Park at Thurgoona, we have constructed outdoor fitness zones on the site.

skate profile
Regional Skate Park

2021/2022 Budget: $2.6M

Total budget: $3.1M

Completion: December 2021

Construction works is well underway on the Albury Regional Skate Park in David Street.

Image of road works sign
Lavington Drain Reconstruction

2021/2022 Budget: $150,000

Completion: December 2021

This project objective is to fully reconstruct the open concrete drain.

Image of road works
Road and drain rehabilitation

2021/2022 Budget: $3.5M

Completion: June 2021

As always, maintaining our road and drain networks will be a major focus of the 2021-22 budget.